Simulations: 9:00 - 9:01 Intro Mike 9:00 - 9:15 Monte Carlo work Matt 9:15 - 9:30 Muon fluxes Jim 9:30 - 9:45 Spallation Bkgnds - Hannah 9:55 - 10:10 2 vs. 3 zone, E calibration - Josh Sensitivity Estimates: 10:10-10:35 Osc. Sensitivities Jon 10:35-10:55 WMA Sensitivities Janet Break: 10:55-11:10 Engineering Reports: 11:10-11:30 Civil Engineering Plan Ed (for Chris) 11:30-12:05 Detector Engineering - Vic, Jim, Steve Other Reports: 12:05-12:25 VSPLAT Exp. Janet Discussion of Proposal 12:25-12:45 Overall Plan Discussion Lunch 12:45-1:30 Discussion of Proposal: 1:30-3:15 Reports from Writers with discussion Break 3:15-3:30 3:30-4:30 Baseline decisions & other feedback 4:30-5:00 Feedback from Braidwood 5:00-6:00 Discussion of plan and schedule for proposal Other talks: MIT Activities Peter
Video and audio: We will use the ESNET IP Ad-hoc bridge as we did for the last meeting.
Video: dial 826763 at 384 kbs Voice only: 1-510-883-7860; at the prompt enter 826763 follwed by # sign.