Thursday Braidwood phone meeting

From: Ed Blucher (blucher@hep.uchicago.edu)
Date: Wed Apr 13 2005 - 09:01:04 CDT


Dear Colleagues,

We will have the first of two phone meetings this Thursday at 10:30 EDT.
To connect to the meeting, dial 1-510-883-7860; at the prompt enter
826763 follwed by the # sign.

   To prepare for the upcoming (but still unscheduled) NUSAG review, we need
to refine and make more specific many aspects of our Engineering/R&D
proposal. We believe updating several sections of the document will be
a useful way to organize the new information. To facilitate the
discussion at Thursday's phone meeting, it would be helpful if primary
authors for different sections of the proposal reread their sections. Some
possible additions/refinements to the proposal are listed below.

   Thursday's meeting will begin with brief reports from the working groups.
We will then discuss our goals for the next few weeks.

Ed and Mike

   Updates to the proposal should include the following.

Revisions/refinements of the baseline design:
  - Gd concentration. Should we change baseline concentration to 0.2%?
  - Real design for veto system.
  - Calibration momvement system design
  - Improved design of underground areas
  - Refined vessel support, neck design (if available)
  - Rough surface design (if available)
  - Final depth in mwe (using bore hole data)

Additions/improvements to proposal text

Clearer discussion of sensitivity. We should provide a more detailed
table of systematic errors. We must
provide justification for the acceptance systematic error (e.g., what is our
strategy for measuring volumes, etc.)

Backgrounds:
We need to provide a complete discussion of backgrounds,
describing the role of the veto system in reducing and measuring backgrounds,
and giving estimates of remaining background levels (both levels and
estimated uncertainties on each background source).
The in-situ monitor section needs to be quantitative, and we should explain
how these measurements affect overall background uncertainties.

Calibration:
  - Include strawman calibration system design (mentioned above)
  - Is source calibration necessary in buffer region?
  - Expand discussion of dissolved sources.

Cross checks:
  - Add possibility of using isotope production from cosmic muons
    to measure fiducial mass.
  - Improve detector movement section to make role of this cross-check clearer.

Incorporate discussion of bore hole information in civil
engineering section.

Incorporate any available updates to mechanical engineering discussion.

Elastic scattering measurement. Incorporate results of several recent
studies in writeup. We need to understand additional costs and requirements
required by this measurement. (The elastic scattering measurement will be
discussed in detail at the second phone meeting.)